31/12/2020
In progress until the end of the project 31/07/2021 and subsequently for the project final reporting activity.
12/23/2019
The Auditor was identified and the procedure was finalized.
09/30/2019
The tender has been prepared to select the Auditor for the Ticino Park Beneficiary.